SHBE will review the list of capital projects

The North Dakota Council on Higher Education will be asked in the coming months to review eleven proposed capital projects to forward to the governor and legislature for possible funding.

A draft 2023-2025 document was presented to the Budget and Finance Committee on Thursday. Projects are the number one priority for each of the eleven institutions.

The UND is considering decommissioning the Hyslop Sports Center and repurposing the site into a science…engineering…and national security corridor. The decision requests $8.8 million in general funds and $2.2 million in other funding.

The eleven projects combined total more than $202 million in state support.
The committee took no formal action on the claims this week.

CAPITAL PROJECT APPLICATION RECOMMENDATIONS:
BSC 1 Multipurpose Academic/Athletic Performance Center $28,500,000 $22,000,000 $6,500,000 New construction/demolition of existing building. Does not increase the overall footprint of the facility.
DCB 1 Old Main/Centre for Rural Health Ed. Note: $4 million was approved in 2021. Additional GFA funding of $975,000 is requested. $975,000 $975,000 Major renovation of existing building/infrastructure. Does not increase overall facility footprint
DSU 1 Agriculture and Technical Education Bldg. $7,200,000 $4,800,000 $2,400,000 Major renovation of the existing building with possible expansion.
LRSC 1 Wind turbine gearbox replacement $350,000 $350,000 Repair of existing infrastructure. Does not increase the overall footprint of the facility.
MaSU 1 Old Main Renovation $39,649,100 $39,649,100 Major renovation of existing building/infrastructure. Does not increase the overall footprint of the facility.
MiSU 1 Dakota Residence Hall Demolition $725,000 $725,000 Demolition of existing building. Reduces overall facility footprint.
NDSCS 1 Agriculture, Automation and Autonomous Systems Technology Initiative $18,171,405 $18,171,405 Major renovation of existing buildings/infrastructure. Does not increase the overall footprint of the facility.
DNSU 1 Engineering Building $98,000,000 $73,500,000 $24,500,000 New construction/demolition of existing building. Does not increase the overall footprint of the facility.
VCSU 1 McCarthy Hall Renovation $8,486,000 $6,486,000 $2,000,000 Major renovation of existing building/infrastructure. Does not increase the overall footprint of the facility.
WSC 1 Medical/Healthcare Building $36,600,000 $26,600,000 $10,000,000 New construction expands overall facility footprint.